Pulsair Valve: Testing and Inspection
Combination valve, checking
Special tools and equipment
- VAG1390 hand vacuum pump
Test requirements
- No DTCs in DTC memory
- Output Diagnostic Test Mode (DTM) performed
- No leaks in vacuum lines or hose connections
- Vacuum hoses not clogged or kinked
Test sequence
- Remove engine cover -1-. To do so, remove 3 bolts (arrows).
- Disconnect vacuum hose from Secondary Air Injection (AIR) solenoid valve (N112).
- Connect VAG1390 hand vacuum pump at vacuum hose (arrow) to combination valve.
Note:
- Do not use pressurized air for the following test!
- Remove intake hose to Secondary Air Injection (AIR) pump motor at upper air filter housing (arrow) and blow into it with light pressure. Combination valve must close.
- Operate vacuum pump. Combination valve must open.
If combination valve does not open:
- Replace Combination valve.