Positive Crankcase Ventilation: Testing and Inspection
Positive Crankcase Ventilation (PCV) System:
INSPECTION
1. REMOVE V-BANK COVER
2. INSPECT PCV VALVE
a. Remove the PCV valve.
b. Install a clean hose to the PCV valve.
c. Inspect the PCV valve operation.
1. Blow air into the cylinder head side, and check that air passes through easily.
CAUTION: Do not suck air through the valve. Petroleum substances inside the valve are harmful.
2. Blow air into the intake manifold side, and check that air passes through with difficulty.
If operation is not as specified, replace the PCV valve.
d. Remove the clean hose from the PCV valve.
e. Reinstall the PCV valve.
1. Apply adhesive to 2 or 3 threads.
Adhesive:
Part No. 08833-00070, THREE BOND 1324 or equivalent
2. Reinstall the PCV valve.
Torque: 27 N.m (275 kgf.cm,20 ft.lbf)
HINT: After applying the specified torque, rotate the PCV valve clockwise with the port faced in the direction indicated in the illustration.
3. Install the PCV valve cover to the PCV valve.
4. Connect the PCV hose to the PCV valve.
3. INSPECT HOSES, CONNECTIONS AND GASKETS
Visually for cracks, leaks or damage.
5. REINSTALL V-BANK COVER