| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
| Replace |
| All Connecting Rods | 14.7 | 10.6 | A | Includes: R&R Cylinder Head, Oil Pan & Plastigauge Bearings. |
| Note |
| To Overhaul Cylinder Head, Add |
| One Bank | 8.7 | 6.2 | A | |
| With E.C.S., Add | 0.4 | 0.2 | A | |
| Add Following Operations If Performed With Piston & Ring Jobs |
| Main Bearings, Renew | 6.4 | 0.0 | A | |
| Crankshaft, Renew | 6.4 | 0.0 | A | |
| Oil Pump, Renew | 2.9 | 0.0 | A | |
| Oil Pump Screen, Clean | 0.2 | 0.0 | A | |
| Rear Main Oil Seal, Renew | 2.2 | 0.0 | A | |
| Rocker Arm Assembly, Renew |
| Right Bank | 0.6 | 0.0 | A | |
| Left Bank | 0.9 | 0.0 | A | |
| Timing Belt, Renew | 1.8 | 0.0 | A | |
| Camshaft, Renew |
| Right Bank | 2.1 | 0.0 | A | |
| Left Bank | 2.3 | 0.0 | A | |
| Tune-Up | 0.5 | 0.0 | A | |