Piston Ring: Labor Times

Standard HoursManufacturer Warranty HoursSkill LevelNotes
Replace
Manual Trans
One Cylinder
Right Bank27.619.6AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Left Bank27.619.7AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Both Banks32.622.9AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Each Additional0.40.3AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
All Cylinders
Right Bank29.221.0AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Left Bank29.221.1AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Both Banks36.00.0AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Auto Trans
One Cylinder
Right Bank28.820.2AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Left Bank28.820.3AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Both Banks32.623.5AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Each Additional0.40.3AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
All Cylinders
Right Bank30.421.6AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Left Bank30.421.9AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
Both Banks36.00.0AIncludes: Remove Cylinder Top Ridge, Deglaze Cylinder Walls And Clean Carbon.
NOTE
To Grind Valves, Add
Both Sides4.63.4A
To R&R Piston, Pin or Connecting Rod, Add
One0.20.0A
Each Additional0.10.0A
All0.80.0A
To R&R Connecting Rod Bearings, Add
Each0.10.0A