| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
| Resurface/Grind |
| Right Bank | 10.8 | 7.6 | A | Includes: R&R Cylinder Head, Grind All Valves & Seats And Mark All Necessary Adjustments. |
| Left Bank | 10.8 | 7.9 | A | Includes: R&R Cylinder Head, Grind All Valves & Seats And Mark All Necessary Adjustments. |
| Both Banks | 15.7 | 11.4 | A | Includes: R&R Cylinder Head, Grind All Valves & Seats And Mark All Necessary Adjustments. |
| Add the Following Operations If Performed With Valves, Grind |
| Tune-Up | 0.6 | 0.0 | A | |
| Valve Guides, Ream |
| Each | 0.2 | 0.0 | A | |
| Valve Guides, Renew |
| Each | 0.2 | 0.0 | A | |
| Lifters, Renew |
| Right Bank | 1.9 | 0.0 | A | |
| Left Bank | 1.9 | 0.0 | A | |
| Both Banks | 2.7 | 0.0 | A | |
| Camshaft, Renew |
| Right Bank |
| One | 1.3 | 0.0 | A | |
| Left Bank |
| One | 1.2 | 0.0 | A | |
| Timing Chain, Renew | 2.1 | 0.0 | A | |